Print shop production schedule. One sheet that's true by 8:15.

The Garment Gopher Team · October 26, 2026

Wednesday, 2:15. The softball league's coach is at the front counter asking if the shirts are done. You look at the whiteboard. It says the job is waiting on art.

The art was approved Saturday. The blanks came in Monday. The job has been on the press since lunch. The board just doesn't know any of that, because nobody who touched the job was standing next to the board when they did.

That's how most shop schedules go bad. Not all at once. One job at a time, until up front stops trusting the board and starts walking back to the press to ask. Here's a free sheet that fixes the board part, and the habits that keep it true.

Print the production schedule

Two pages. Page one is the job board: a line for every open job, sorted by due date, with pieces, prints, method, a box for what it's waiting on, and the press day. Page two is the week: each press day with its capacity and the jobs planned on it, so you can see Thursday is full before you promise Thursday.

On a phone, pick Print, then Save as PDF. Start a fresh one every Monday.

Why the board falls behind

A whiteboard is a fine tool. Plenty of good shops run on one, plus a file drawer of work orders by date. It falls behind for three plain reasons.

The person who changes the job isn't at the board. The art approval comes in on someone's phone. The blanks get checked in at the back door. The press operator finishes a run at 4:50 and goes home. Every one of those is a real change, and none of them happened in front of the board.

It lists jobs in the order they came in. The job written at the top is the oldest, not the one due first. So the eye lands on the wrong job every time.

It mixes jobs that can run with jobs that can't. A job waiting on a deposit sits right next to one with everything in the building, and they look the same. You can't plan a press day off that.

Set the sheet up by due date

One line per job. Write them in due date order, soonest at the top. When a new job comes in with an earlier date, it goes on the line where it belongs, even if that means rewriting a few lines. That's why the sheet starts fresh every Monday: copying ten open jobs onto a clean page takes five minutes and puts them back in order.

Count prints, not just shirts. Forty-eight hoodies with a front and a back is 96 prints. Two 50-shirt jobs can be an hour apart on the press or half a day apart, and the print count tells you which.

One letter for what it's waiting on

A lot of paper shops already do this: a letter next to the job that says what's holding it. Pick yours and put the key at the top of the sheet. Ours:

The rule that makes the letters worth writing: a job only gets a press day when the only letter left is P. Everything else is a phone call or a box that hasn't come yet, and you can't print a phone call.

The letters also turn the sheet into a to-do list. Every A is a customer to nudge. Every D is a deposit to ask for. Every G past its arrival date is a supplier to call. Run down the column once and you know who you're calling before lunch.

Fill press days by prints, not by due dates

Due dates tell you the order. They don't tell you whether it fits. For that you need one number: how many prints your crew really does in a press day, counting loading, changeovers and cleanup.

Don't guess it. Time one ordinary day and divide. Say a two-person crew on one manual press gets 300 one-color prints done in a day, setup and all. That's your shop's number, not anybody else's, and it's the number that goes at the top of each day on page two.

Then add up the prints planned for each day. If Thursday has the 96-print hoodie job, a 150-print church job and a 72-print team job, that's 318. Over your 300. Something moves to Friday now, on paper, instead of at 5:30 Thursday with three people standing around.

Five colors run slower than one. Write down what your crew got through on the last multi-color job and plan those off that number.

The 10-minute morning check

First thing, before the phones start, whoever runs production and whoever runs the front stand at the sheet for ten minutes and answer three questions.

What's late, or due in three days? Circle it. Those jobs get talked about first, every morning, until they're gone.

What's waiting on something we can fix today? Read down the letter column. Assign every A, D and late G to a person before you walk away.

What's on the press today, and is all of it here? Blanks counted, screens burned or transfers in, approved mockup on the work order. If anything's missing, today's plan changes now, at 8:15, while there's still a day to work with.

And one rule for the rest of the day: whoever changes a job writes it on the sheet before they walk away. Pen, not memory. If it isn't on the sheet, the next person to look doesn't know it.

What the sheet won't do

Paper is honest about its limits. It only knows what somebody wrote on it, it only lives in one place, and up front still has to walk to it to read it. With a handful of open jobs, that holds up. In the busy season it slips, because the board needs updating faster than anybody walks past it.

The schedule is one piece of getting a job out the door. Each line on it should point to a work order that travels with the box. Every G on the sheet comes from an order day, and a blank order tally keeps those orders from coming in short. If orders are still arriving by text and DM before they ever reach the board, our free t-shirt order tracker gives you an order log for the front end.

This is step eight of the whole order: scheduling the press from one board. Our print shop order management guide walks every order from the first text to pickup, one step at a time, with a free job folder sheet.

Where Garment Gopher fits

In Garment Gopher the board is already in due date order. Ground Control shows every job with its due date, status, project, customer, total and piece count. Jobs In Production sit at the top, then everything else by soonest due. Overdue jobs show red, and jobs due in the next three days show amber, so the first morning question answers itself.

Instead of letters, every job has a status: Draft, Calculate Art Charge, Awaiting Approval, Awaiting Deposit, Approved: Order Supplies, Waiting on Supplies, In Production, Needs Delivered, Invoiced and Paid. Each one comes with a plain next step, like ticking Deposit received when the Venmo or PayPal notice or the cash comes in. When a customer approves the quote online, the board shows who approved it and when, and the job moves on its own. Ticking the deposit or Paid moves it too. Everything else you change by hand from a dropdown, which is the same rule as the paper: whoever moves the job changes the status.

Jobs waiting on blanks get Apparel and Transfers rows with Ordered and Received boxes and an expected arrival date, and a late one turns red. The top of the board counts active jobs, jobs that need ordering and overdue jobs, and the board refreshes every two minutes. Click a due date to change it.

It's the same board on every computer and phone in the shop, and everybody gets their own login at no extra charge. Up front can see a job is In Production without walking back to the press.

It won't plan your press days. There's no capacity number in it. You still decide what runs Thursday, and page two of the free sheet still does that job.

It's $79 a month for the whole shop, and the first 14 days are free with no card.

Start my free 14 days
© 2026 Garment Gopher LLC · GarmentGopher.com · Dig out of paperwork. Get back to business. · Call or text 563-210-0678 · support@garmentgopher.com · Blog
Production Schedule
Every open job, soonest due at the top. Start fresh every Monday.
Week of
Press capacity (prints per day)

Waiting on: A = art approval · D = deposit · G = garments · T = transfers or screens · P = ready for press or on it · R = ready for pickup. Only a P gets a press day.

DueJob #CustomerGarment and colorPiecesPrintsMethodWaiting onPress dayDone

Whoever changes a job writes it here, in pen, before they walk away. Free production schedule from GarmentGopher.com

This Week on the Press
Add up the prints. If a day is over capacity, move a job now.
DayCapacity (prints)Jobs planned (job #)Prints plannedOver or underMoved to
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
☐ Late or due in 3 days circled☐ Every A, D and late G has a name on it☐ Today's jobs have blanks, screens or transfers, and an approved mockup
Morning check notes